National Commission For The Certification Of Crane Operators - NCCCO

Home

Handbooks & Forms

CCO Store

Contact Us Login
Test Dates & Locations

Find out when and where the next tests are being administered.

Computer Based Testing (CBT)
Subscribe
 

Subscribe to our news mailing list to keep up with NCCCO News and Industry Headlines.
Subscribe Today!

Certification Quick Links
Mobile Crane Operator Tower Crane Operator Overhead Crane Operator
Signalperson Rigger

Articulating Crane Operator

Signalperson

 
 
Certification Programs

Overview | Mobile Crane Operator | Tower Crane Operator | Overhead Crane Operator
Articulating Crane Operator | Digger Derrick Operator | Signalperson | Rigger
Crane Inspector

 

Crane Inspector
Certification Policies | How Do I Test?

Mobile Crane Inspector Exam Outline

Core Crane Inspector | Mobile Crane Inspector | Tower Crane Inspector | Overhead Crane Inspector | Reference Material

The following are sample test questions typical of the style and content of the questions used in NCCCO Written Examinations.

  1. According to OSHA 1926 Subpart CC, how long are records of monthly crane inspections required to be retained?

    a. One month

    b. Three months

    c. Six months

    d. Twelve months


  2. Unless the manufacturer specifies otherwise, crane masts should be erected plumb to a tolerance of

    a. 1:250

    b. 1:500

    c. 1:750

    d. 1:1000

  3. If a qualified person determines a deficiency needs to be monitored, the employer must ensure the deficiency is checked at what intervals?

    a. Daily

    b. Each shift

    c. Weekly

    d. Monthly

  4. If during the pre-erection inspection, the qualified person doing the inspection finds a crane component that is damaged or worn to the extent that it would create a safety hazard if used, the damaged component must not be used until it is repaired and:

    a. Evaluated by the crane owner

    b. Evaluated by the crane user

    c. Re-inspected by the qualified person

    d. Re-inspected by the operator

  5. According to OSHA 1926 Subpart CC, which category I operational aid is required on mobile cranes manufactured after December 16, 1969?

    a. Anti two-blocking device

    b. Load limiting device

    c. Boom angle limiting device

    d. Boom hoist limiting device

 

Question #

Answer

1

B

2

B

3

D

4

C

5

D

 